    For week ending May 13, 2022

    1. Routine work HR, bank admin
    2. Habot launch July 1 review
    3. ATB exercise UI and UX dataflow and coding started
    4. Habot pages end document fields and deconstruction
    5. Product features must be linked to tasks
    6. Financials biweekly meeting started and focus on breakeven

    For next week ending May 20, 2022

    1. Routine work
    2. Provide encouragement to the Habot launch team
    3. Breakeven and tightening the financial analysis and actions in the biweekly reviews
    4. Shift in management style to meeting targets continues
    5. Wire diagram feedback continuously
    6. Media plan for awareness and launch